pull down to refresh

CORPUS CHRISTI, Texas — After hours of public testimony, heated debate and several arrests in the audience, the Corpus Christi City Council on Wednesday voted against advancing what would have been the city’s most expensive infrastructure project to date: a $1.2 billion desalination plant at the Inner Harbor.
Welp this project is dead
Key Amendment Fails
The pivotal decision came with the rejection of Amendment 5, which would have allowed contractor Kiewit to move forward with design plans to 60% completion. The amendment also called for the company to return with a guaranteed maximum price by March 2026.
What got people so worked up? I assume the people arrested were all against the plant?
reply